UV Cipp Pipelining Project on Apartment Complex in Albany, NY

Area under the tub after being re-piped with new PVC.

Albany – NY. A large management company in the Capital Region was for a solution to some sewer line issues they were having. The issue took place inside of the many apartment buildings on the property, and it began with a leaking tub drain. One of our Trenchless technicians began a camera inspection from the toilet flange in the bathroom, and found that the bottom of the 4″ cast iron sewer line had completely deteriorated.

Water had begun pool underneath the tub due to this, and started making the issue worse. Our technician determined that the best solution was to install a new epoxy coating from the toilet flange in the bathroom over to the 4′ sewer main roughly 10ft away. After the new line was installed, the crew also exposed the broken tub drain, and replaced that with PVC as well. Additionally while on site the crew discovered additional issues within the main trunk line of the building. A camera inspection revealed that near one of the lateral tie ins there was a hole in the sewer line, causing additional problems.

The crew determined that descaling the pipe, then installing a new UV Inversion pipe, roughly 30′ long. After the new liner is cured they would then cut back in three reinstatements for lateral lines, and ensure 100% flow of all sewer lines leading to the trunk line. The job collectively took about 1-2 days to complete, but it was spread out over the course of 1-2 weeks. This included mobilization, set up, prep work, and breakdown.

Technician set up in one of the service locations, during the UV curing process.
Technician set up in one of the service locations, during the UV curing process.
Area underneath the tub prior to be re-piped.
Area underneath the tub prior to be re-piped.
Area under the tub after being re-piped with new PVC.
Area under the tub after being re-piped with new PVC.
Post lining - where the end of the new liner meets the original cast iron sewer line.
Post lining – where the end of the new liner meets the original cast iron sewer line.
Post Coating - End of toilet drain line, where it goes into the main cast iron trunk line. This is the 45 degree fitting going downward towards the main.
Post Coating – End of toilet drain line, where it goes into the main cast iron trunk line. This is the 45 degree fitting going downward towards the main.
Pre Lining - A section of sewer line where there is a slight shift in the pipe, which made a lip going around the inside diameter of the pipe. This can cause things to get caught up, and then cause sewer back ups.
Pre Lining – A section of sewer line where there is a slight shift in the pipe, which made a lip going around the inside diameter of the pipe. This can cause things to get caught up, and then cause sewer back ups.

Post Lining - Section of the sewer line after the new liner has cured.
Post Lining – Section of the sewer line after the new liner has cured.
After Lining Lip
After Lining Lip
After Coating Lip
After Coating Lip
Facebook
Twitter
LinkedIn
Pinterest