We Saved The 3″ PVC Water Lines at a Popular Fun Park in NY

Pond Inspection4

THE PROBLEM: There were two sections of broken 3″ PVC water line that go to the fountains under the mini golf course at the Latham, NY Fun Park.

THE SOLUTION: Two 5ft UV pipe lining patches were installed, and camera-inspected after completion.

HOW LONG DID IT TAKE? Job duration was roughly one full day.

WHAT TOOLS WERE USED? The crew used Permaliner LR3 UV lining products for this job.

 